Tasmania’s new AFL stadium has suffered another cost blowout, causing the premier to break a promise to cap the state’s spend as critics fear the end price will be far higher.
The cost estimate for the 23,000-seat roofed venue at Macquarie Point in Hobart has increased from $1.13 billion to $1.23 billion.
On top of the figure is $132 million for broader precinct infrastructure, project delivery costs of $183 million and unspecified contingencies, taking the total to $1.54 billion.
Premier Jeremy Rockliff previously pledged to cap Tasmania’s contribution to the build at $875 million as part of a deal to get the project through parliament.
But he conceded on Tuesday the state would have to cover the slated $100 million increase via extra borrowings.
“The previous cost estimate, which we announced … some 14 months ago, there’s been a lot of water under the bridge since that point,” Mr Rockliff said.
The premier confirmed the project wouldn’t head back to parliament for the approval of the necessary extra funding, despite previous assurances it would.
The latest estimate reflects increases in the cost of construction, sustained high oil and materials prices, higher labour costs and its complexity, the state government said.

The stadium is expected to be ready for the 2031 AFL season and was a condition of the Tasmania Devils being granted a licence to enter into the national competition in 2028.
It initially had a price tag of $715 million.
Mr Rockliff said the state had reached out to the federal government and AFL for extra money on top of their $240 million and $15 million contributions.
Anti-stadium group Our Place Hobart said the new cost estimate failed to take into account other factors, including the interest bill and the exact cost of contingencies.

Greens leader Rosalie Woodruff described the ongoing cost increases as a deep betrayal of Tasmanians.
“Who knows where the final price for the stadium will end up?” she said.
“What we do know is there’s been now a fifth major cost blowout and there’s not yet a contract price locked in for this massive project.”
Federal independent MP Andrew Wilkie fears the stadium will end up costing $2 billion.
“Once you add the cost of the debt over a decade, the total cost to the Tasmanian taxpayer is closer to $3.5 billion,” he said.

Devils chief executive Brendon Gale said the question of any additional funding from the AFL was a matter for the sport’s governing body.
“The politicians can politic. We’ll get on with building our club,” he said.
“People have their views and are entitled to them. But based on my experience, people never look back. These types of projects transform cities and states.”
The release of updated costs came ahead of schedule after the government bowed to political pressure to make the figures public before the end of the parliamentary year.

In mid-October, BESIX Watpac was announced as the preferred builder. A final contract is set to be signed by the end of 2026.
BESIX Watpac recently built a 30,000-seat roofed stadium in Christchurch in New Zealand which cost about $540 million.
Mr Rockliff said the final contract price for the Hobart stadium was unlikely to differ from the $1.23 billion estimate.
The stadium has been deeply divisive in Tasmania amid rising state debt, a stretched health system and other under-pressure services.
The AFL and federal government have been contacted for comment.